How to Create a Validate Report in PCS

Once logged into PCS, navigate to Data Exchange > Spatial Web Entry.

2025-11-25_13-34-30

Navigate to the desired Grower, Farm, Field, and Year, then select Nutrients from the dropdown and click the "Load" button.

2025-11-25_14-21-12

If you need to use an Overlay Layer, you can select it.

2025-11-25_14-22-29

Using the Dropdowns, select the data to Overlay.

2025-11-25_14-22-47

Once satisfied, click the "Add Overlay Layer" button.

2025-11-25_14-23-07

Select the polygon to carve out the trial area by clicking on the map and then click on the tool on the left-hand side.

2025-11-25_14-30-12

Click outside of the polygon to start to split the polygon.

2025-11-25_14-32-10

Click the last point to stop the drawing and then click the "Split Polygon" button.

2025-11-25_14-33-19

Continue to carve out the area until satisfied.  

2025-11-25_14-35-07

If the area is contain within the polygon, you may have split out a polygon "path" to accomplish this.

 

Once the area is selected, click the "Edit button.

2025-11-25_14-37-50

Using the Dropdown and select "Check, Test, or Other".  If "Other" is selected, type in the box what you want displayed on the Validate report.  Click the "OK" button.

2025-11-25_14-39-07

Now carve out the area that you would like check against the Test/Other area by using the same procedure as above.

2025-11-25_15-05-39

Click the "Save Layer Changes" button.

2025-11-25_15-06-42

After a few moments, navigate to the Field Reports page, select the hierarchy & year of the field that you just worked with, and select either the Validate or Validate with Management Zones report.

2025-11-25_15-08-52

You can View or Download this Report.

2025-11-25_15-16-54

If you have any questions, don't hesitate to contact your Advisor Support Representative.